WORK SCHEDULE

Weekly Work Schedule: Beginning Sunday night
5-11-08 thru Thursday night 5-16-08  we will be installing new granite edging in the median between Cypress St. and Boylston Place which will result in left lane closures on Route 9 eastbound and westbound. We will also be installing new granite edging in the median near Norfolk St. on Route 9 WB, which will result in left lane closures. This crew will then move to removing and resetting vertical curbing between Tully St. and Hammond St.
Additionally we will be preparing the median for Bituminous Concrete between Warren St. and Boylston Place resulting in left lane closures on Route 9 eastbound and westbound. This crew will then start the sidewalk excavation between Tully St. and Hammond St. resulting in right lane closures on Route 9 EB.
We will also be installing Bituminous Concrete in the median between Lee St. and High St. resulting in left lane closures on Route 9 WB and EB.

Note: The scheduled replacement of sidewalk  between Tully St. and Hammond St. will begin this week with sidewalk excavation, and vertical curbing being removed and reset.

Please drive safely and obey all posted speed limits while passing through work zones. Thank You.

Aggregate Industries appreciates your patience during this construction process.

Due to the high volume of emails we have received regarding construction work in the Chestnut Hill Mall area we would like to clarify that the area in which we are working begins at the Newton Town line and ends at High Street in Brookline. 

 

PLEASE SUBMIT YOUR COMMENTS AND FEEDBACK >>

Work Schedule

To minimize traffic and delays, this project is intended for mostly nighttime work between the hours of 8:00pm and 5:00am. Some types of work, including sidewalk and median work, will occur in daylight hours and may require single lane closures and or parking restrictions..

Due to the significant volume of traffic on this roadway, MassHighway has contracted for much of this project to occur at night. Work is scheduled for Sunday through Thursday nights each week.  Work will not typically be performed on Friday or Saturday nights. Work crews will typically deploy on the roadway following the evening rush hour and will remain active through the night, clearing the roadway each morning before the morning rush hour. 

Speed limits on this project are 35 mph, and be advised that there are certain areas within the project where speed limits are lower.

We will announce specific work schedules throughout the project through the schedule feature of this website.

Please sign up for email alerts of our specific work schedules if you are interested in receiving up to date work schedule advisories.